Stakeholder management and project management office: Effect on project results
Main Article Content
Abstract
Managing stakeholders is relevant for project management, as they affect project results. Likewise, the support of a Project Management Office (PMO) improves these results. This study analyzes the positive influence of stakeholder management
on project results, specifically on the likelihood of concluding projects within the predicted time and cost, together with the moderating effect of PMOs. A conceptual model was validated through logistic regression, with data collected through a survey
responded by 216 experienced professionals studying in graduate programs on project management. Findings indicate that stakeholder management improves project results in terms of time and cost and confirm that PMO enhances the influence of stakeholder management on these results. As its contribution, the study reinforces stakeholder management and PMO as key elements for successful project management. Sampling was sufficient for research replicability but restricted to professionals of project management living in Peru. Thus, future studies could target a broader population.
Downloads
Metrics
Article Details
A RAE compromete-se a contribuir com a proteção dos direitos intelectuais do autor. Nesse sentido:
- adota a licença Creative Commoms BY (CC-BY) em todos os textos que publica, exceto quando houver indicação de específicos detentores dos direitos autorais e patrimoniais;
- adota software de detecção de similaridades;
- adota ações de combate ao plagio e má conduta ética, alinhada às diretrizes do Committee on Publication Ethics (COPE)
References
Aaltonen, K., & Kujala, J. (2016). Towards an improved understanding of project stakeholder landscapes. International Journal of Project Management, 34(8), 1537-1552. doi: 10.1016/j.ijproman.2016.08.009
Agresti, A. (2019). An introduction to categorical data analysis. In D. J. Balding, N. A. C. Cressie, G. M. Fitzmaurice, GeofH. verificar Givens, H. Goldstein, G. Molenberghs, D. W. Scott, A. F. M. Smith, & R. S. Tsay (Orgs.), 390pp 3rd ed.. Hoboken, USA: Wiley.
Aladpoosh, H., Shaharoun, A. M., & Saman, M. Z. B. M. (2012). Critical features for project stakeholder management: A systematic literature review. International Journal of Applied Systemic Studies, 4(3), 150. doi: 10.1504/IJASS.2012.051130
Aragonés-Beltrán, P., García-Melón, M., & Montesinos-Valera, J. (2017). How to assess stakeholders’ influence in project management? A proposal based on the Analytic Network Process. International Journal of Project Management, 35(3), 451-462. doi: 10.1016/j.ijproman.2017.01.001
Aubry, M. (2015). Project management office transformations: Direct and moderating effects that enhance performance and maturity. Project Management Journal, 46(5), 19-45. doi: 10.1002/pmj.21522
Basten, D., Stavrou, G., & Pankratz, O. (2016). Closing the stakeholder expectation gap: Managing customer expectations toward the process of developing information systems. Project Management Journal, 47(5), 70-88. doi: 10.1177/875697281604700506
Bourne, L. (2015). Making projects work: Effective stakeholder and communication management. Retrieved from https://www.crcpress.com/Making-Projects-Work-Effective-Stakeholder-and-Communication-Management/Bourne/p/book/9781482206661
Bredillet, C., Tywoniak, S., & Tootoonchy, M. (2018). Exploring the dynamics of project management office and portfolio management co-evolution: A routine lens. International Journal of Project Management, 36(1), 27-42. doi: 10.1016/j.ijproman.2017.04.017
Brunet, M., & Forgues, D. (2019). Investigating collective sensemaking of a major project success. International Journal of Managing Projects in Business, 12(3), 644-665. doi: 10.1108/IJMPB-08-2018-0167
Chow, V., & Leiringer, R. (2020). The practice of public engagement on projects: From managing external stakeholders to facilitating active contributors. Project Management Journal, 51(1), 24-37. doi: 10.1177/8756972819878346
Cleland, D. I. (1985). A strategy for ongoing project evaluation. Project Management Journal, 16(3), 11-17. Retrieved from https://www.pmi.org/learning/library/strategy-ongoing-project-evaluation-1798
Creswell, J. W., & Creswell, J. D. (2017). Research design: Qualitative, quantitative, and mixed methods approaches. Thousand Oaks, USA: SAGE Publications.
Dai, C. X., & Wells, W. G. (2004). An exploration of project management office features and their relationship to project performance. International Journal of Project Management, 22(7), 523-532. doi: 10.1016/j.ijproman.2004.04.001
Davis, K. (2016). A method to measure success dimensions relating to individual stakeholder groups. International Journal of Project Management, 34(3), 480-493. doi: 10.1016/j.ijproman.2015.12.009
Dinsmore, P. C. (1999). Winning in business with enterprise project management. New York, USA: AMACOM.
Eskerod, P., & Vaagaasar, A. L. (2014). Stakeholder Management strategies and practices during a project course. Project Management Journal, 45(5), 71-85. doi: 10.1002/pmj.21447
Freeman, R. E. (1984). Strategic management: A stakeholder approach. Boston, USA: Pitman.
Hair Jr, J. F., Black, W. C., Babin, B. J., & Anderson, R. E. (2019). Multivariate data analysis (8th ed.). Hampshire, UK: Cengage Learning.
Hartman, F. T. (2000). The role of TRUST in project management. PMI® Research Conference 2000. Retrieved from https://www.pmi.org/learning/library/role-trust-project-management-1095
Heravi, A., Coffey, V., & Trigunarsyah, B. (2015). Evaluating the level of stakeholder involvement during the project planning processes of building projects. International Journal of Project Management, 33(5), 985-997. doi: 10.1016/j.ijproman.2014.12.007
Ika, L. A., & Donnelly, J. (2017). Success conditions for international development capacity building projects. International Journal of Project Management, 35(1), 44-63. doi: 10.1016/j.ijproman.2016.10.005
Karlsen, J. T., Græe, K., & Massaoud, M. J. (2008). Building trust in project‐stakeholder relationships. Baltic Journal of Management, 3(1), 7-22. doi: 10.1108/17465260810844239
Lehtinen, J., & Aaltonen, K. (2020). Organizing external stakeholder engagement in inter-organizational projects: Opening the black box. International Journal of Project Management, 38(2), 85-98. doi: 10.1016/j.ijproman.2019.12.001
Littau, P., Jujagiri, N. J., & Adlbrecht, G. (2010). 25 years of stakeholder theory in project management literature (1984-2009). Project Management Journal, 41(4), 17-29. doi: 10.1002/pmj.20195
Maddaloni, F. Di, & Davis, K. (2017). The influence of local community stakeholders in megaprojects: Rethinking their inclusiveness to improve project performance. International Journal of Project Management, 35(8), 1537-1556. doi: 10.1016/j.ijproman.2017.08.011
Maddaloni, F. Di, & Davis, K. (2018). Project manager’s perception of the local communities’ stakeholder in megaprojects. An empirical investigation in the UK. International Journal of Project Management, 36(3), 542-565. doi: 10.1016/j.ijproman.2017.11.003
McGibbon, S., Abdel-Wahab, M., & Sun, M. (2018). Towards a digitised process-wheel for historic building repair and maintenance projects in Scotland. Journal of Cultural Heritage Management and Sustainable Development, 8(4), 465-480. doi: 10.1108/JCHMSD-08-2017-0053
Mitchell, R. K., Agle, B. R., & Wood, D. J. (1997). Toward a theory of stakeholder identification and salience: Defining the principle of who and what really counts. Academy of Management Review, 22(4), 853-886. doi: 10.5465/amr.1997.9711022105
Mok, K. Y., Shen, G. Q., & Yang, J. (2015). Stakeholder management studies in mega construction projects: A review and future directions. International Journal of Project Management, 33(2), 446-457. doi: 10.1016/j.ijproman.2014.08.007
Müller, R., Drouin, N., & Sankaran, S. (2019). Modeling organizational project management. Project Management Journal, 50(4), 499-513. doi: 10.1177/8756972819847876
Müller, R., Glückler, J., & Aubry, M. (2013). A relational typology of project management offices. Project Management Journal, 44(1) 59-76. doi: 10.1002/pmj.21321
Olander, S., & Landin, A. (2005). Evaluation of stakeholder influence in the implementation of construction projects. International Journal of Project Management, 23(4), 321-328. doi: 10.1016/j.ijproman.2005.02.002
Oliveira, G. F. de, & Rabechini, R. J. (2019). Stakeholder management influence on trust in a project: A quantitative study. International Journal of Project Management, 37(1), 131-144. doi: 10.1016/j.ijproman.2018.11.001
Pemsel, S., & Wiewiora, A. (2013). Project management office a knowledge broker in project-based organisations. International Journal of Project Management, 31(1), 31-42. doi: 10.1016/j.ijproman.2012.03.004
Pinto, J. K., Slevin, D. P., & English, B. (2009). Trust in projects: An empirical assessment of owner/contractor relationships. International Journal of Project Management, 27(6), 638-648. doi: 10.1016/j.ijproman.2008.09.010
Project Management Institute. (2017). Um guia do conhecimento em gerenciamento de projetos (Guia PMBOK®) (6a ed.). Newtown Square, USA: PMI. Project Management Institute.
Rose, J., & Schlichter, B. R. (2013). Decoupling, re-engaging: Managing trust relationships in implementation projects. Information Systems Journal, 23(1), 5-33. doi: 10.1111/j.1365-2575.2011.00392.x
Saad, A., Zahid, S. M., & Muhammad, U. B. (2020). Role of awareness in strengthening the relationship between stakeholder management and project success in the construction industry of Pakistan. International Journal of Construction Management, 1-10 doi: 10.1080/15623599.2020.1742854
Sergeeva, N., & Ali, S. (2020). The role of the Project Management Office (PMO) in stimulating innovation in projects initiated by owner and operator organizations. Project Management Journal, 51(4), 440-451. doi: 10.1177/8756972820919215
Shenhar, A., Dvir, D., Levy, O., & Maltz, A. (2001). Project success: A multidimensional strategic concept. Long Range Planning, 34, 699-725. doi: 10.1016/S0024-6301(01)00097-8
Sperry, R. C., & Jetter, A. J. (2019). A systems approach to project stakeholder management: Fuzzy cognitive map modeling. Project Management Journal, 50(6), 699-715. doi: 10.1177/8756972819847870
Vuorinen, L., & Martinsuo, M. (2019). Value-oriented stakeholder influence on infrastructure projects. International Journal of Project Management, 37(5), 750-766. doi: 10.1016/j.ijproman.2018.10.003
Walker, D., & Rowlinson, S. (2019). Routledge handbook of integrated project delivery. London, UK: Routledge.
Wit, A. de. (1988). Measurement of project success. International Journal of Project Management, 6(3), 164-170. doi: 10.1016/0263-7863(88)90043-9
Xue, H., Zhang, S., Su, Y., Wu, Z., & Yang, R. J. (2018). Effect of stakeholder collaborative management on off-site construction cost performance. Journal of Cleaner Production, 184, 490-502. doi: 10.1016/j.jclepro.2018.02.258
Yang, R. J., & Shen, G. Q. P. (2015). Framework for stakeholder management in construction projects. Journal of Management in Engineering, 31(4), 04014064. doi: 10.1061/(ASCE)ME.1943-5479.0000285